Langsung Electric's Nigeria Free Trade Zone Company Expected to Complete Construction and Begin Operations by Year-End
Langsung Electric FZE (Langsung Electric FZE) started construction in March 2020, overcoming the impact of the pandemic and challenges such as transportation difficulties. The administrative building and ground floors of the second and third factories have been completed, with an overall completion rate of 80%. It is expected to finish construction and begin operations within this year.
The overall construction is progressing steadily. Electrical and water supply works are expected to be completed by April, and full renovation is scheduled for May, making the site ready for installation. Full completion is anticipated by June, with official production expected to start in August.




Langsung Electric's Nigeria Free Trade Zone Company is located in the Lekki Free Trade Zone in Lagos, covering an area of 30,000 square meters. Upon completion, it will have an annual design capacity of $100 million. Rooted in Africa, the company will promote industry development through advanced technology, high-quality products, and comprehensive services, contributing to the acceleration of Africa's industrialization.
Feb 5, 2021